Аннотация: The Story about the interest in the Bureya theme on January 31, 2019
The Story about the interest in the Bureya theme on January 31, 2019
1) About increase in level of attention to "The Bureya problem".
"On January 31 the governor of the Amur region Vasily Orlov took off by helicopter for Khabarovsk Krai, to the place where in riverheads Bureya the hill slope collapsed. The head of the region told about it in the Instagram.
"... Now the main thing ... to make everything to reduce risks" - Vasily Orlov wrote ... " [https://asn24.ru/news/crime/59344/?utm_source=yxnews&utm_medium=desktop] [http://www.teleport2001.ru/news/2019-01-31/108115-gubernator-vasiliy-orlov-otpravilsya-k-mestu-zagadochnogo-opolznya-na-reke-buree.html?utm_source=yxnews&utm_medium=desktop]
2) Information on works on elimination of a natural dam on the Bureya River.
"Official site of the Government of Khabarovsk Krai
On January 31, 2019 8:40:15 PM
Military prepare the next blasting a landslide in Verkhnebureinsky district ...
On the place of a landslide engineering troops of the Ministry of Defence of the Russian Federation plan to carry out one more series of explosions. After the fourth 50 tons of TNT blasting it was succeeded to do the channel of 17 meters in depth in a blockage.
The part of the canal leaves under ice, approximately on 3 meters.
It is expected that soon ... will manage to create the passage, sufficient for restoration of the normal hydrological mode of the Bureya River ...
The rocky fragments which remained after explosions remove by means of heavy machinery. In three changes [In three shifts] the bulldozer and excavators fulfill the clearing the passage for water...
... The authorities of the region introduced the emergency regime and resolve an issue with resettlement.
Press service of the governor and government of Khabarovsk Krai" [https://www.khabkrai.ru/events/news/172880]
"Ministry of Defence of the Russian Federation
31.01.2019 (05:00)
The task for military engineers is in that between two pools the connection was formed, and a water went. The total amount of soil and rocks which should be removed for functioning of the channel is about 90 thousand cubic meters. About 80 thousand cubic meters are at the moment removed.
Four blastings are earlier executed, after which depth channels was 17 meters from initial level, length - 145, and width - about 35 meters." [https://function.mil.ru/news_page/country/more.htm?id=12215196@egNews]
"www.amur.info
On January 30, 2019, 17:46
Military punched to a channel on the Bureya River (video)
Military engineers of the Eastern Military District carried out large-scale blasting a layer of rocky masses around the Bureya anomaly. This time more than 56 tons of TNT are used. It was succeeded to form the channel which is at the moment 2.5-3 meters lower than ice level ...
The Amur air base continues to help military.
On January 29 the aircraft delivered to the place of dislocation of the military personnel generators, building materials, food and fuel and lubricants.
Also to the place of blastings the hydrologist and the geologist were brought. The Amur rescuers are on duty on access roads to a reservoir and on the Talakan Embankment.
Only from 22 till 29 January engineering troops of the Ministry of Defence of the Russian Federation carried out 5 blastings, 129 tons of explosives are spent..." [http://www.amur.info/news/2019/01/30/149317]
3) Forecasts for a subject about prospects of the decision to "The Bureya problem".
"On January 31, 2019,
The fourth explosion: the military will break through the natural dam [the military will create the channel for the river water]
Today, 21:52
On the first of February on the place of a landslide which blocked the Bureya River in Khabarovsk Krai, the fourth large explosion is planned. Military expect to provide a through current of water. In the Bureya district prepare for succession of events.
As noted by a hydropower experts the wave will reach the Bureyskaya HPP during the day, however the dam [of the power station] of serious consequences will not feel.
Flooding also does not threaten the settlements of Priamurye. The main concern is caused by fans of winter fishing. On Thursday, January 31, a situation in the territory the Amur governor Vasily Orlov examined.
The settlement of Talakan lives expectation. The group of rescuers of the ministry of natural resources, the Ministry of Emergency Situations, police and also experts of the Bureya district work round the clock. The emergency mode remains since January 18. If efforts of military are crowned with success, then today-tomorrow tension has to decline. The main thing - not to allow on ice of people. According to rescuers and hydropower engineering specialists, water after the break can to go on [above] the surface of ice. Then will not seem a little to all [people] who will appear on the way [of water].
- In eleven days on ice of the Bureya Reservoir tried to pass more than 500 people, 46 cars. 26 fishermen are expelled from a reservoir. Total number of airmobile group reaches 102 persons, 46 pieces of equipment are involved. The population is constantly informed on radio and television on danger of an exit to ice - the chief of the Ministry of Emergency Situations of Russia of the Amur region Matvei Gibadulin reported.
Readiness of operational services was estimated by the head of the region Vasily Orlov. To the place of a landslide he took off by helicopter. As it was reported on the place of events, the work is going hard due to climatic conditions. The Bureya HPP allocated to help the military a vehicles and a bulldozer equipment.
- We do the cleaning of soft soil which was formed after explosive works. Works are conducted in the round-the-clock mode under the general management of military command, - the head of group of technical supervision of Nizhnebureysky hydroelectric power station Dmitry Luchnikov reported.
- Severe conditions. The equipment fails, and people work, - the director of the branch of PJSC RusHydro the Bureya hydroelectric power station Alexander Garkin confirmed ...
During the operational meeting at the Bureya hydroelectric power station, cautious forecasts were made about the subsequent development of events. As Alexander Garkin noted, the hydroelectric power plant is ready to regulate the generation of electricity depending on the water level. By April 20, when the natural flood begins, hydrology should reach the natural level.
The head of the region was asked for assistance with specialized drilling equipment [for drilling of the soil]: the drills should be compact so that they can be delivered to the landslide site by transport helicopters. To completely disassemble the soil that blocked of the Bureya, it will need more time. In the meantime, the main task is to bring the river bed to normal. At the same time, the Bureya Reservoir is already able to accept any volume of water...
According to the Amur minister of forestry and fire safety Alexey Venhlinskiy, there is no threat of flooding of settlements of area, even if to assume that water will begin to be poured through a dam [of the hydroelectric power station]. The settlement of Talakan and other settlements of the Bureya district are much above the threatened level.
- Our main task - safety of people - the governor Vasily Orlov emphasized. - Potentially waterlogged are listed the settlement New Bureya [Novobureisky], the villages of Malinovka and of Nikolaevka. At the same time experts are sure that nothing threatens them.
At the same time we consider any possible scenarios, including possible evacuation of people is fulfilled. We have an understanding whom where to take out and where to place.
Within two-three days after break of the natural dam a monitoring of consequences will be carried out. In case of favorable succession of events the emergency mode in the region will be removed ...
The delegation of the government of the Amur region arrived not empty-handed. During flight of zone emergency by the military gifts - several boxes with apples, cookies, juice were transferred.
Also the governor held a meetings with the population of the Bureya district...
The Amur geologist and the hydrologist began work on the place of blasting a landslide on the Bureya River in Khabarovsk Krai. Experts and also generators, building materials (boards, iron), food and fuel and lubricants were delivered yesterday, on January 29, by the Mi-8 helicopter of the Amur air base.
According to the press service of the government of the region, all forces and means of a regional territorial subsystem of RSChS are in high alert. Rescuers in Priamurye continue to be on duty on access roads to the reservoir and on Talakan River Embankment.